Diversion tunnels have been completed to redirect the Peace River during low water this summer and fall, in one of the most critical steps to completing the Site C dam, March 2020. (BC Hydro)

Diversion tunnels have been completed to redirect the Peace River during low water this summer and fall, in one of the most critical steps to completing the Site C dam, March 2020. (BC Hydro)

B.C. Hydro’s Site C set back by COVID-19, foundation changes

Peace River diversion still on track for this fall

B.C. Hydro’s plan to have the third dam on the Peace River complete and in service by 2024 has been set back by work scaling down due to COVID-19 restrictions on construction projects, and additional foundation strengthening for the powerhouse and spillway.

In a progress report filed with the B.C. Utilities Commission July 31, B.C. Hydro CEO Chris O’Riley says the Site C project is still on track to divert the Peace River through a pair of tunnels and begin in-river work. But that too has been complicated by geological conditions. The financial impact of the coronavirus delays and additional work will be better known in the fall, O’Riley said.

“Pandemic-related delays will present further cost pressure on the budget,” O’Riley wrote in a letter to BCUC chair David Morton. “As the evolution of the pandemic is uncertain and the date of resolution is unknown, various cost and scheduled impact scenarios continue to be assessed and refined as part of the re-baselining process.”

The incoming NDP government reluctantly decided to carry on with Site C, after former premier Christy Clark vowed to push the project “past the point of no return” before the 2017 B.C. election. In doing so, Premier John Horgan approved an updated cost estimate of $10.7 billion to complete it, an increase of about $1 billion from the initial estimate.

RELATED: Site C dam project carries on under NDP government

RELATED: NDP pays off $1.1B in B.C. Hydro debt, seeks rate cut

RELATED: After losing at every level, West Moberly sues again

Now the combined effects of COVID-19 and a series of problems have pushed the cost up by an amount not yet known. Those issues included changes to the main civil works contract, increased costs of reservoir clearing, power line construction and highway realignment, and first nations treaty infringement claims and an injunction application.

“Towards the end of December 2019, investigations and analysis of geological mapping and monitoring activities completed during construction identified that some foundation enhancements would be required to increase the stability below the powerhouse, spillway and future dam core areas,” O’Riley wrote.

Before the COVID-19 pandemic, Site C was on track for completion by fall 2023 and full service to the B.C. Hydro grid by 2024.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislatureCoronavirusSite C

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Dr. Paul Stent is the first physician in Fort St. James to have received the vaccine, Jan. 22. (Northern Health photo)
Fort St. James receives shipment of COVID-19 vaccine

First vaccination clinics were held Jan. 22.

The COVID-19 outbreak at the two Coastal GasLink workforce lodges has officially been declared over. (Lakes District News file photo)
COVID-19 outbreak at Coastal GasLink worksites declared over

In total, 56 cases were associated with the outbreak in the Burns Lake and Nechako LHAs

Fort St. James municipal office. (File photo)
Fort St. James byelection Q&A with candidates

Here are the answers from Brenda Gouglas and Bradley Miller

Brett Alexander Jones is wanted on several warrants province-wide, in connection with multiple charges. Jan. 21, 2021. Kitimat RCMP photo
Kitimat RCMP searching for man wanted on several warrants province-wide

Jones is described as a five-foot 10-inches Caucasian man, with blond hair and blue eyes.

Toronto Public Health nurse Lalaine Agarin sets up for mass vaccination clinic in Toronto, Jan. 17, 2021. B.C. is set to to begin its large-scale immunization program for the general public starting in April. THE CANADIAN PRESS/Frank Gunn
B.C.’s COVID-19 mass vaccinations expected to start in April

Clinics to immunize four million people by September

Chief Public Health Officer Theresa Tam speaks during a daily briefing in Ottawa. (THE CANADIAN PRESS/Adrian Wyld)
31 cases of COVID-19 variants detected in Canada: Health officials

Dr. Theresa Tam made announces 13 more variant COVID-19 cases in Canada

Daily COVID-19 cases reported to each B.C. health region, to Jan. 20, 2021. Island Health in blue, Northern Health green, Interior Health orange, Vancouver Coastal in red and Fraser Health in purple. (B.C. Centre for Disease Control)
B.C.’s COVID-19 infection rate stays stable with 508 cases Friday

Vaccine delivered to more than 110,000 high-risk people

The District of Saanich’s communications team decided to take part in a viral trend on Thursday and photoshopped U.S. Senator Bernie Sanders into a staff meeting photo. (District of Saanich/Twitter)
Bernie Sanders makes guest appearance municipal staff meeting in B.C.

Vancouver Island firefighters jump on viral trend of photoshopped U.S. senator

Cannabis bought in British Columbia (Ashley Wadhwani/Black Press Media)
Is it time to start thinking about greener ways to package cannabis?

Packaging suppliers are still figuring eco-friendly and affordable packaging options that fit the mandates of Cannabis Regulations

School District 57 headquarters in Prince George. (Mark Nielsen, Local Journalism Initiative Reporter)
Prince George school district settles with sexual abuse victim

Terms were part of an out-of-court settlement reached with Michael Bruneau, nearly four years after he filed a lawsuit

Surrey provincial court. (File photo: Tom Zytaruk)
New COVID-19 protocols set for provincial courthouses

The new rules were issued on Jan. 21, and took effect immediately

Police in Vancouver looking for male suspect who allegedly spat and attacked a store manager for not wearing a mask, at 7-Eleven near Alma Street and West 10th Avenue just before noon on Dec. 17, 2020. (Vancouver police handout)
VIDEO: Man spits on 7-Eleven manager over mask rule, sparking Vancouver police probe

‘Unfortunately, the store manager sustained a cut to his head during the assault’

The Vancouver-based SAR team successfully rescued two lost snowshoers off of the west side of Tim Jones Peak in the early morning of Monday, Jan. 19. (North Shore Rescue photo)
B.C.’s busiest SAR team raises alarm after 2021 begins with fatality, multiple rescues

‘People beyond ski resort areas of Seymour, Grouse, and Cypress go without cell reception,’ SAR warns

Most Read