Construction of the 19 km Spuzzum section of the Interior-Lower Mainland transmission line

Merritt-Coquitlam power line completed

A year behind schedule and over-budget, high-voltage line subject to arbitration between BC Hydro and its contractor

A year behind schedule and $18 million over budget, the latest high-voltage line of the BC Hydro grid has been completed from Merritt to Coquitlam.

The new line parallels the existing main line supplying the Lower Mainland and Vancouver Island from hydro dams on the Peace and Columbia Rivers. It was originally to be completed in 2014, but the main contractor fell behind and BC Hydro used its own crews to complete one of the most difficult portions, a 19 km stretch north of Hope.

The final cost for the 247 km line is expected to be $743 million, which Energy Minister Bill Bennett said is about two per cent more than the initial $725 million budget.

“There is an ongoing arbitration between BC Hydro and [contractor] Flatiron Graham as to who’s going to bear the cost of the delay, because the project was delayed by a year,” Bennett said in an interview Friday.

It’s the first 500-kilovolt line added to the BC Hydro grid in 40 years, to keep up with demand from a growing southwestern B.C. population and increase reliability in the event of disasters.

“You always have the potential for a big avalanche or a mudslide, even an earthquake, to take out one or two of your big transmission lines, bringing electricity in from the two rivers, the Columbia and the Peace,” Bennett said.

NDP energy critic Adrian Dix said the project started out with a $600 million estimate, making it $143 million over budget. He said it’s the latest in a series of cost overruns, including the Northwest Transmission Line north of Terrace, the Dawson Creek-Chetwynd line and the Iskut extension in the northwest.

Bennett said BC Hydro is under-budget on its overall capital construction plan, including $100 million under budget on reconstruction of five generating units at the W.A.C. Bennett Dam on the Peace River, and there is no additional effect on rates.

BC Hydro is committed to a capital budget of $2.4 billion a year for the next 10 years, including construction of the Site C dam on the Peace River and reconstruction of the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island.

 

Just Posted

Crews increasing containment, Shovel Lake fire

The fire hasn’t moved closer to Fort St. James on the east or north sides

Shovel Lake wildfire, highway 27 and pipeline

It’s close to one and reached another

‘Beauty amongst such tragedy:’ B.C. photographer captures nature’s trifecta

David Luggi’s photo from a beach in Fraser Lake shows Shovel Lake wildfire, Big Dipper and an aurora

Four-legged evacuees, Vanderhoof

Local physician opens up her property for 60 dogs and numerous horses

Kids, seniors at risk as smoke from distant fires hangs over parts of B.C.

B.C. Centre for Disease Control says children’s lungs don’t fully develop until about age 10

B.C. mother charged in 7-year-old daughter’s death appears in court

The 36-year-old mother, of Langley’s Aaliyah Rosa, has been charged with second-degree murder

VIDEO: Teen soccer phenomenon Alphonso Davies to visit B.C. kids camp

The 17-year-old Vancouver Whitecap player is one of the youngest players in MLS history

New plan to lift more than two million people past the poverty line

Anti-poverty strategy will aim for 50 per cent cut in low-income rates: source

Liberals scrap lottery system for reuniting immigrants with their parents

Lottery for parent sponsorship to be replaced, more applications to be accepted

Bear kills off-leash dog in B.C. park

There have been nearly 200 pet or livestock and bear encounters so far this year

Trudeau says he won’t apologize to heckler, pledges to call out ‘hate speech’

Prime Minister had accused woman of racism as she shouted about illegal immigration at Quebec rally

Most Read