Coastal GasLink stops work on section of pipeline route

Internal audit reveals clearing took place without valid archaeological impact assessments in place

Map of pipeline route showing location of Section 8 on which work has been stopped due to discrepencies with archaeological impact assessments. Coastal GasLink graphic.

Coastal GasLink (CGL) has stopped work on the last section of its pipeline project which runs from roughly south of Hazelton to Kitimat due to discrepencies with its archaelogical impact assessments.

In a statement on its website tonight, the company said it had discovered during an internal audit two areas where clearing has taken place in Section 8 contrary to its permits from the BC Oil and Gas Commission (OGC).

“At KP (kilometre post) 585, an area of approximately 600 metres long by 50 metres wide was cleared without an approved AIA in place,” the statement reads. “Areas adjacent to this location did have an approved AIA and were identified as low likelihood of archaeological significance. While clearing activities have taken place, minimal ground disturbance has occurred since the area has been used for transit and corduroy mats had been placed to limit disturbance.

READ MORE: NEB rejects federal review of Coastal GasLink pipeline

“At KP 631, due to a re-route, an area of approximately 240 metres by 10 metres was cleared without an AIA being completed. Areas adjacent to this location did have an approved AIA and were identified as low likelihood of archaeological significance”

CGL says it has voluntarily disclosed these incidents to (OGC), and the Environmental Assessment Office (EAO) and First Nations groups affected.

“Coastal GasLink is committed to protecting the environmental and cultural values of British Columbia during construction and operation of our natural gas pipeline,” said David Pfieffer, CGL president.

READ MORE: Gidimt’en launch civil lawsuit against Coastal GasLink

“Coastal GasLink regrets the errors that led to construction activities taking place without having approved archaeological impact assessments in place prior to start of construction.

“I have directed the team to complete a thorough investigation of these incidents and have halted clearing work in the area until the investigation is complete and recommendations are put into practice.

“I have also apologized to the impacted Indigenous communities and requested their participation in a proposed post-impact assessment.”



editor@interior-news.com

Like us on Facebook and follow us on Twitter

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Pipeline at centre of B.C. conflict is creating jobs for First Nations: chief

All 20 elected band councils along the Coastal GasLink pipeline route have signed benefits agreements

Job placement office open in Fort St. James

Office being opened for forestry workers affected by mill closures

RCMP create access control checkpoint on Morice West Forest Service Road

Premier says Coastal GasLink project will proceed despite opposition

Horgan says ‘rule of law applies,’ Coastal GasLink will proceed despite protests

The 670-kilometre pipeline is part of a $40 billion liquefied natural gas project

Extreme cold warning in effect for Stuart-Nechako region

It’s been a cold weekend and the frigid conditions are going to… Continue reading

Kids across Canada more at risk of hospitalization from flu this season: doctor

Dr. Theresa Tam said influenza B does not usually peak until February or later

Closed mills, housing surge support a positive forecast for lumber industries

B.C. lumber producers have closed mills accounting for 18% of province’s capacity, RBC report says

Good Samaritan pays part of rent for B.C. woman facing eviction in can-collecting dispute

Zora Hlevnjak, 76, supplements her pension by collecting cans and receiving public donations

Kelowna’s ‘Baby Mary’ finds biological parents after more than 30 years

Geneologist and DNA test helped her connect with her biological parents

Kelowna hotel to award couples for baby-making with Nooner deal

The deal includes a free stay every Valentine’s Day for the next 18 years

‘Scariest boat ride of my life’: Passengers trapped by ice on rocky B.C. ferry sailing

The Nimpkish docked in Bella Coola on Jan.12 coated in a thick layer of ice

B.C. pair ordered to pay $55,000 for oil tank discovered four years after selling home

Judge says defendants breached contract, despite being unaware of tank until basement flooded

Canada to give $25,000 to families of each Canadian who died in Iran plane crash

Prime Minister Justin Trudeau also made it clear that Canada still expects Iran to compensate victims

Oil and gas industry applauds top court’s dismissal of B.C.’s Trans Mountain case

The high court’s ruling Thursday removes one of the remaining obstacles for the project

Most Read