Harvie Campbell

Delayed but still going forward

The Fort St. James Energy plant planned to begin construction this spring was delayed, but is still a go, according to the company.

People may have noticed a lack of activity on the site planned for the The Fort Energy project on Tachie Road.

The bioenergy plant, which would burn wood waste to produce electricity, planned to start construction this spring has been pushed back at least a year, but according to Western BioEnergy Director Harvie Campbell, they still hope to go ahead.

European markets and booming oil and gas in Fort MacMurray are both factors in the delay, but not the only ones, according to Campbell.

“I think it’s just normal development delays,” he said. “I would expect that it would be spring of next year (to be on site constructing).”

Part of the delay he said is due to some decision-making which needs to take place  involving choosing the specific boiler and turbine to be used. The equipment will be used in both the Fort St. James plant and a Merritt plant, where the company was approved to build a plant essentially a “carbon copy” of the one planned for Fort St. James. The Merritt plant is similarly delayed.

Another aspect of the delay has to do with capital construction costs and securing a contractor.

Construction of the large bioenergy plants requires similar construction expertise and equipment to that used in the Fort MacMurray-based oil industry. Therefore, with the booming oil and gas industry, demand is making these companies harder to secure.

The European economic troubles creating uncertainty in the markets has also made financing more difficult for these types of projects, according to Campbell. He expects the project to be financed for approximately 70 to 80 per cent of the capital costs, which he said is normal for these types of projects.

Campbell said the goal is to secure the financing by December of this year, with on-site construction then aimed for spring of next year, once the snow is off the site.

Hiring of employees would take place after construction began.

Operation of the plant would begin 24-27 months after construction begins.

Western BioEnergy Inc. is 20 per cent owned by Dalkia, which will also be the operator of the plant, and 80 per cent owned by Fengate Capital out of Toronto.

Both the Merritt and Fort St. James projects will produce about 40 megawatts of electricity, and use wood waste which would otherwise be

left in the bush, or burned in piles.

Previous stories on Fort St. James bioenergy plant:

Bioenergy approved for Fort St. James

Not a rubber stamp

Bioenergy coming to the north

 

Just Posted

Fire ban back in effect for Northwest Fire Centre region

Starting May 24, both Category 2 and Category 3 prohibitions will be in place

New Seven Sisters replacement confirmed

Mental health facility will have 25 beds, up from 20 in current facility

Convicted animal abuser to return to B.C. court May 21

Catherine Jessica Adams is facing a breach of probation charge

Gallery: Project Heavy Duty inspires students into it’s 32nd year

The event is a collaboration between SD91 and industry in and around Vanderhoof, Fraser Lake and Fort St. James

Telkwa pot plant application passes review

Cannabis company claims new Health Canada regulations are working in its favour

B.C.’s fight to regulate bitumen through pipelines to go to Canada’s top court

BC Appeal Court judges found B.C. cannot restrict bitumen flow along Trans Mountain pipeline

Scheer says it would take Conservatives five years to balance budget

Scheeraccused the Liberal government of spending $79.5 billion of previously unbudgeted funds

B.C. man, 30, arrested for driving his parent’s cars while impaired twice in one day

The Vancouver-area man was arrested after officers caught him driving impaired twice in one day

New airline regulations bring compensation for tarmac delays, over-bookings

Some of the new regulations will roll out in July, while others are expected for December.

More than half of Canadians support ban on handguns, assault rifles: study

Divide between rural and urban respondents in latest Angus Reid Institute public opinion study

Spring rain needed as B.C. sees one of the lowest snowpack levels in 40 years

Snowpack levels in B.C. recorded on May 15 were similar to those in 2015 and 2016

Theresa May to quit as party leader June 7, sparking race for new PM

The new Conservative leader will become prime minister without the need for a general election

B.C. man who fell off cliff returns there to rescue eagle from vulture attack

Nanaimo’s James Farkas, who broke his hip in a fall, saves eagle on same beach months later

Raptors beat Bucks 105-99 to move within 1 game of NBA Finals

Leonard scores 35 as Toronto takes 3-2 series lead over Milwaukee

Most Read