The recycling centre built by the Greening up Fort St. James Society was destroyed by fire in the early morning on Monday.

Phoenix from the ashes…GUF makes plans to rebuild their recycling centre and revamp their strategic plan for the future

Greening Up Fort St. James Society will be rebuilding after a fire destroyed their recycling facility.

“Don’t give up, because we’re coming back bigger and stronger.”

Louise Evans-Salt, spokesperson for Greening Up Fort St. James Society (GUF), gave the announcement recently the group will be rebuilding after a fire destroyed their recycling facility.

The building may even be rebuilt sooner and have less of a financial shortfall than was originally feared.

So far, the group has learned the total cost of a rebuild will be around $90,000, and would include two fire-rated steel doors instead of the wood construction doors the first building had.

They have also learned the concrete slab poured for the building will not have to be demolished and replaced.

“We’re really fortunate we don’t have to replace the slab because that would have been big money,” said Jana Gainor , GUF recycling coordinator.

The demolition and landfilling of the concrete and rebar was estimated in the thousands.

Instead, the slab will only have to be capped to repair some minor gouging which damaged the surface.

The group also saved some money on their cleanup costs thanks to Brad Miller of BAM BAM trucking. Miller generously donated nearly three days of cleanup on the site, which included the use of equipment, a crew and hauling the materials to the dump. Miller also had his staff separating the insulation and wood from the metal roofing in order to recycle the metal.

Gainor said the contribution was huge.

So while the group will still be looking at a shortfall, it appears it may be in the area of less than $10,000, where they previously had worried it could be in the tens of thousands.

As for the time frame to get the new recycling centre built, Gainor said a contractor they have spoken to expects to be able to complete the build within two months of starting it, and would be able to start sooner than she had initially anticipated.

She is hopeful they may be able to get the new building done as soon as the end of August.

In the meantime, GUF is still looking at setting up a temporary site for fibre collection and Riverside Repairs has also offered to help out by donating their property for the temporary facility.

A shelter Riverside erected on their property could house the bailer and recyclable fibre, if GUF can purchase the bailer before the building is completed.

Not being able to accept fibre in the meantime is a concern for the group.

“That’s a challenge and we know that the Fort St. James community has really made a commitment to recycle,” said Evans-Salt.

She hopes people are willing to help to store the fibre for the time being or pool fibre with friends driving through area communities which still have facilities such as Vanderhoof or Prince George.

“Don’t fill up the landfill,” said Evans-Salt, urging people to help the community continue to reduce its waste.

The group met with partners last week, including Mount Milligan, who were just starting a recycling program in partnership with GUF not long before the facility burned.

The group is now looking at updating their strategic plan to adjust for the setback and to see where they should go from here.

“How do we grow the recycling initiative, how do we prevent another setback or crisis,” said Evans-Salt.

Along these lines, the group held a public meeting at the public library last week, getting input from the community on what they would like to see from the group, and they also hope to increase membership and raise further funds through a membership drive.

“Finances is a big issue,” said Evans-Salt. “We’re definitely going to have to increase our funding base.”

As a volunteer-driven, nonprofit organization, the group will now be working to make up the shortfall for the cost to rebuild through various fundraising efforts.

While the news is good the group will be able to rebuild, there are still going to be some hurdles, as the fire has set the group back significantly from where they had hoped to be.

Aiming to make themselves self-sustaining within two and a half years of starting the building with the funding they had in place, the fire will likely set the group back a year.

“Basically, it gives us less time to become self-sustaining,” said Gainor.

By the end of 2013, the group will need enough money to continue to operate. This may also be impacted by the new Product Stewardship legislation which will come into effect, changing the structure of recycling in the province. But no one is yet sure exactly what the legislative changes will mean in practice.

Previous stories on the fire and GUF:

Arson investigation into recycling centre fire

Fire destroys recycling centre

Fort gets greener for Earth Day

 

Just Posted

More B.C. ambulance service needed in the North: Hospital chief of staff

Fort St. James physicians talk about the need for easier access to healthcare

Broken axle caused New Hazelton train derailment: TSB

It could happen again without a different way to inspect trains

Cullen remains uncertain about political future

Says he’ll make decision in early March

Terrace resident’s bill banning single-use plastics introduced in Ottawa

MP Nathan Cullen’s presented Ben Korving’s private member’s bill Wednesday

B.C. BUDGET: Surplus $374 million after bailouts of BC Hydro, ICBC

Growth projected stronger in 2020, Finance Minister Carole James says

VIDEO: Iconic ‘snow cone’ takes shape at B.C. park near Clearwater

Snow cone forming at Wells Gray Provincial Park one that would make Disney’s Queen Elsa proud

Pink Shirt Day a reminder to ‘T.H.I.N.K.’ before posting on social media

‘Be Kind’ message on shirts sold for anti-bullying activities of Wednesday, Feb. 27

A ‘warm embrace’ for grieving parents at funeral of seven young fire victims

Mourners offered love and support to Kawthar Barho, mother of seven children

Indigenous leaders, politicians say Trans Mountain report flawed

The National Energy Board has endorsed an expansion of the Trans Mountain pipeline a second time

UPDATE: Reports of rashes prompt closure of all Harrison Hot Springs pools

Public pool available after Fraser Health shut down all five mineral pools until further notice

Legislation to protect B.C. farmland comes into effect

Regulations enhance food security, encourage long-term farming

Have you heard the legend of Shuswaggi, the Shuswap Lake monster?

Witness accounts as old as 1904, and as recent as 2018, place a creature in the lake’s depths

UPDATE: B.C. ticket holder winner of $25.9-million Lotto Max jackpot

Next draw set for Mar. 1 with an estimated jackpot of $10 million

B.C.-based ‘Team Tardi’ brings home gold in junior curling worlds

In a 9-4 victory over Switzerland, a Langley-based curling team earned its 2nd straight world title

Most Read